The segment of the project through The Colony’s city
limits is referred to as the FM423 South
Project. The project includes auxiliary right and left turn lanes at specific
locations along Main Street, and a
new signal at Lake Highlands Blvd.
The project is funded by the North Central
Council of Governments and Denton County. If you have
any questions, please contact Brant Shallenburger at 972-624-3108 or
the Engineering Department at 972-624-3195 or via email at engineering@thecolonytx.gov
.
|
-
The roadway construction
contract was conditionally approved by TxDOT in
September 2011.
-
Construction is scheduled to
start mid to
late 2013 after the private utilities have
completed relocation.
-
Anticipated completion date
is June 2016.
-
Oncor, CoServ, AT&T, Grande, LISD, and Time Warner are
relocating private utilities.
-
City Council approved
agreements for TxDOT’s contractor to construct
enhancements and relocate the City’s
utilities.